Inspection Status: Partial Pass
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 01/29/2024 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
1/29/24: North, south, west, and spread footings are properly dug with rebar reinforcement and steel columns bolt forms in place. 11 column footings are properly dug with rebar reinforcement and bolt form in place. Elevator pit forms are in place with rebar reinforcement and angle iron supports for drain plate. Okay to proceed with concrete footings pour in these locations. |
| 02/01/2024 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Passed |
|