Inspection History: COT - HCBU - Building Progress

Permit Number - TC-COM-0223-00619

Inspection Description - COT - HCBU - Building Progress

Inspection Status - Not Ready

Date Description Inspector Results Comments
01/16/2024 COT - HCBU - Building Progress Not Ready
06/25/2024 COT - HCBU - Building Progress Passed
08/16/2023 COT - HCBU - Building Progress Partial Pass Partial approval for under ground plumbing and electrical, ok to cover
10/17/2023 COT - HCBU - Building Progress Partial Pass 10/17/23 decking screw inspection ref letter dated 10/3/23 for fastener substitution
10/30/2023 COT - HCBU - Building Progress Partial Pass
11/21/2023 COT - HCBU - Building Progress Partial Pass 11/21/23 underground site lighting between pole bases on west side and north side of building ok to cover
12/14/2023 COT - HCBU - Building Progress Partial Pass Partial approval for under ground plumbing and electrical, ok to cover
10/17/23 decking screw inspection ref letter dated 10/3/23 for fastener substitution.
11/21/23 underground site lighting between pole bases on west side and north side of building ok to proceed.
12/14/23: grease trap bedding inspected passed. Pending connection and testing.