Inspection Status: Passed

Inspection History: COT - HCBU - Preslab  

Date Description Inspector Results Comments
02/12/2024 COT - HCBU - Preslab   Passed
08/24/2023 COT - HCBU - Preslab   Partial Pass Partial for first 1/3 east side ok to place concrete
08/30/2023 COT - HCBU - Preslab   Partial Pass
10/18/2023 COT - HCBU - Preslab   Partial Pass 10/18/23 partial approval for 2nd floor first 2 columns from west to east, ok to place concrete
10/23/2023 COT - HCBU - Preslab   Partial Pass 10/23/23 ok to place concrete next two column lines
10/25/2023 COT - HCBU - Preslab   Partial Pass 10/25/23 partial approval for second floor, third set of columns from west to east OK to place concrete
10/30/2023 COT - HCBU - Preslab   Partial Pass 10/30/23 last section of 2nd floor ok to place concrete