Inspection Status: Passed
Inspection History: COT - HCBU - Preslab
| Date |
Description |
Inspector |
Results |
Comments |
| 02/12/2024 |
COT - HCBU - Preslab |
|
Passed |
|
| 08/24/2023 |
COT - HCBU - Preslab |
|
Partial Pass |
Partial for first 1/3 east side ok to place concrete |
| 08/30/2023 |
COT - HCBU - Preslab |
|
Partial Pass |
|
| 10/18/2023 |
COT - HCBU - Preslab |
|
Partial Pass |
10/18/23 partial approval for 2nd floor first 2 columns from west to east, ok to place concrete |
| 10/23/2023 |
COT - HCBU - Preslab |
|
Partial Pass |
10/23/23 ok to place concrete next two column lines |
| 10/25/2023 |
COT - HCBU - Preslab |
|
Partial Pass |
10/25/23 partial approval for second floor, third set of columns from west to east OK to place concrete |
| 10/30/2023 |
COT - HCBU - Preslab |
|
Partial Pass |