Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Inspection Status: Partial Pass

Inspection History: PDSD Building Division - Site Excavation/Layout/Rebar

Permit Number - TC-COM-0223-00619

Inspection Description - PDSD Building Division - Site Excavation/Layout/Rebar

Inspection Status - Partial Pass

Date Description Inspector Results Comments
06/08/2023 PDSD Building Division - Site Excavation/Layout/Rebar Partial Pass Dan Quinn - Partial pass, Column Lines 2 & 3, - 7-footings in each column lines 2 & 3. OK, to pour.
06/13/2023 PDSD Building Division - Site Excavation/Layout/Rebar Partial Pass Part #2 of box culvert (16’ x 20’). Ok to place concrete in progress areas.
06/16/2023 PDSD Building Division - Site Excavation/Layout/Rebar Partial Pass Box culvert, Part #2 at 16’ x 20’. Ok to place concrete in progress areas.
07/05/2023 PDSD Building Division - Site Excavation/Layout/Rebar Partial Pass for column line 4, south side, ok to place concrete for interior column footers.
parking lighting east and south 1/2 of electrical underground chase, ok to shade and cover.
under slab electric chases in south 1/2 of building ok to shade and cover
07/10/2023 PDSD Building Division - Site Excavation/Layout/Rebar Partial Pass partial approval for two exterior footers grid line 2&3 east side, ok to place concrete
07/13/2023 PDSD Building Division - Site Excavation/Layout/Rebar Partial Pass
07/17/2023 PDSD Building Division - Site Excavation/Layout/Rebar Partial Pass #13 culvert pour
08/02/2023 PDSD Building Division - Site Excavation/Layout/Rebar Not Ready
08/04/2023 PDSD Building Division - Site Excavation/Layout/Rebar Partial Pass
08/08/2023 PDSD Building Division - Site Excavation/Layout/Rebar Not Ready
08/11/2023 PDSD Building Division - Site Excavation/Layout/Rebar Partial Pass
08/21/2023 PDSD Building Division - Site Excavation/Layout/Rebar Partial Pass
08/28/2023 PDSD Building Division - Site Excavation/Layout/Rebar Passed 8/28/23 partial for per slab on middle section, ok to place concrete