Inspection Status: Partial Pass

Inspection History: COT - LCEL - Electrical Final 

Permit Number - TC-COM-0125-00146

Inspection Description - COT - LCEL - Electrical Final 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
07/09/2025 COT - LCEL - Electrical Final  Partial Pass Approved interior sub-panel replacements for Building D, units #100 - #108, units #137, #138, #141, #142, units #200 - #208, units #237 - #242 (28)
No electrical clearances are required
07/11/2025 COT - LCEL - Electrical Final  Partial Pass Approved interior sub-panel replacements for Building D, units #109, #111- #122, units #209 - #223, #225 - #233 (36)
No electrical clearances are required
07/15/2025 COT - LCEL - Electrical Final  Canceled 7/15/2025 canceled per contractor.
07/17/2025 COT - LCEL - Electrical Final  Re-inspection required 7/9/25 - Approved interior sub-panel replacements for Building D, units #100 - #108, units #137, #138, #141, #142, units #200 - #208, units #237 - #242 (28)
No electrical clearances are required
7/11/25 - Approved interior sub-panel replacements for Building D, units #109, #111- #122, units #209 - #223, #225 - #233 (36)
No electrical clearances are required

7/15/2025 canceled per contractor.
7/17/25: wiring must be properly marked at terminals, #6 AWG copper required at all load centers for a 50Amp breaker (Rick stated it was a #8 AWG)
07/29/2025 COT - LCEL - Electrical Final  Passed Approved per G.A. 7/29/2025