Inspection History Details
Inspection Status: Not ready for Inspection
Inspection History: ELECTRIC - TEMP POWER FOR TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/14/2007 | ELECTRIC - TEMP POWER FOR TEST | Not ready for Inspection | 1) YOU NEED #4 GROUNDING ELECTRODE CONDUCTOR CONNECTED TO 2 EACH GROUND RODS. 2) GROUNDING RODS NEED TO BE 6' APART. 3) YOU NEED TO HAVE YOUR TEMP MOUNTING PANEL SECURE. IT MAY NOT ROCK, TWIST, ETC. 4) YOU NEED TO CONNECT YOU METER SOCKET TO THE DISCONNECT PANEL. TEP DOES NOT SUPPLY THE METER SOCKET...ONLY THE WIRE FROM THE METER TO THE POLE. |
|
| 12/11/2007 | ELECTRIC - TEMP POWER FOR TEST | Not ready for Inspection | BUILD TEMP SERVICE PRIOR TO CALLING INSPECTION, MUST BE COMPLETE WITH GROUNDS AND ALL CONNECTIONS. |