| 03/21/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 03/14/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 03/08/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 03/02/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 02/28/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Pot holing has started on Bellevue. |
| 02/23/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - No signs of any work. |
| 05/18/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-Routine Barricade Inspect - Traffic control is set according to plan. |
| 10/17/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Numerous final and temporary patches in the roadway. |
| 09/19/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work ongoing. |
| 09/07/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. Many temporary patches are in the roadways. |
| 08/29/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 08/15/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 08/05/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 07/29/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 07/20/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 02/17/2022 |
TRSP - ROW - Recurring |
|
Passed |
TDOT-EXCAV GENERAL INSPECTION - No signs of any work. |
| 05/11/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-Routine Barricade Inspect - Traffic control is set according to plan. |
| 07/13/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 07/12/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. The picture I took is at Bellevue in Sonoita. This was marked out by Tucson water of the area they need to re-pave because of the unmarked waterline that was hit. |
| 07/06/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 07/01/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - At the intersection of Sonoita and Bellevue, the intersection is not ready to be paved because NPL has not finished in this area. |
| 06/20/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Cold patch was put down in the areas that were destroyed by the hit water line. |
| 06/17/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Tucson water has marked out the areas to be re-paved. I am going to ask them to hold off until southwest gas is through this intersection with their underground. If they do not hold off, I told Southwest Gas they will not be held to moratorium rules at the intersection of Bellevue Street in Sonoita Avenue. |
| 06/17/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Tucson water has marked out their limits for paving. I’m going to ask them to hold off for a while until Southwest Gas gets out of this area with the underground. I told Southwest Gas they will not be held to moratorium rules in this area the intersection of Bellevue st and Sonoita Ave. I am going to call Tucson water to get this area cleaned up. Southwest Gas that they would do a little bit to try to get it drivable. |
| 06/17/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Tucson water has marked out there areas to be re-paved. I’m going to try to get them to hold off a while so Southwest Gas can get their work done in this area. I told Southwest Gas that they will not be held to moratorium rules this is not their fault in this area. Southwest Gas is going to try to clean up the intersection to make it drivable. Tucson water through barricades out here. |
| 06/17/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - A waterline was hit at Bellevue Street and Sonoita Avenue. It was an unmarked water line. According to NPL, Tucson water has taken responsibility for this and they are going to pay to have this re-paved. NPL wants Tucson water to hold off until they are through this intersection. |
| 05/18/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 02/15/2022 |
TRSP - ROW - Recurring |
|
Passed |
TDOT-EXCAV GENERAL INSPECTION - Have pre-con with Southwest gas and NPL. They have given me all of the notifications already. I explained them the rules about compaction, microsealing, barricading and good housekeeping. |
| 05/05/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-Routine Barricade Inspect - Traffic control is set according to plan. |
| 05/11/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 05/05/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 05/02/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 04/26/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 04/20/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 04/15/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. I got a call from contractor on April 14 about extending the job 300 feet. They were not able to make the Tie in where they wanted to so they asked me if they could extend it 300 feet to make the Tie in. I gave them the go ahead and they are applying for a new permit. |
| 04/08/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 04/05/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 03/31/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 03/24/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Work on going. |
| 02/11/2022 |
TRSP - ROW - Recurring |
|
Passed |
TDOT-EXCAV GENERAL INSPECTION - No signs of any work. A Precon is set up for Tuesday the 15th. |
| 05/02/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-Routine Barricade Inspect - Traffic control is set according to plan. |
| 11/15/2022 |
TRSP - ROW - Recurring |
|
Complete (Recurring) |
|
| 07/12/2023 |
TRSP - ROW - Recurring |
|
Passed |
|