Permit: T22RW00054

Parcel: 10304001Q

Inspection Status: Passed

Inspection History: TRSP - ROW - Recurring

Permit Number - T22RW00054

Inspection Description - TRSP - ROW - Recurring

Inspection Status - Passed

Date Description Inspector Results Comments
08/17/2022 TRSP - ROW - Recurring Passed TDOT-EXCAV GENERAL INSPECTION - All electric work completed prior to silverbell widening. No further issues
08/03/2022 TRSP - ROW - Recurring Passed TDOT-EXCAV GENERAL INSPECTION - All electric work completed. Work was done prior to Silverbell widening. Capital project. Any issues were resolved daily.
05/09/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Precon for upcoming work on site
03/15/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - All new poles have been added and are in place. All overhead aerial wire has been installed. Small issue still needed
03/15/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Poles and electric work still in progress. O
02/24/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Pre construction discussion with Noel with Vargas Construction, sub-contractor for TEP. Relocatation of AG and UG electric. 20 poles and 5 new foundations on this stretch. Working from Silverbell and Sweetwater (2 Foundations) and heading south to end. Work to start 2/28 and take 3 weeks.
02/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - All pole bases have been installed. Contractor will fall back and install tops. No issues but traffic has been bad at times.
02/09/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Digging and setting two poles a day. Traffic congestion daily, flaggers are in use. Traffic control removed before 3:30 daily
01/05/2023 TRSP - ROW - Recurring Passed
02/03/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Precon was held prior to construction. Notices were installed along roadway on 4 x 4 post. Pole installation along the west side of Silver Bell. All work is being performed in dirt area. Barricades will be moving daily as work proceeds. Poles are being brought in as needed and not stored on site