Inspection Status: Approved
Inspection History: INSP - FOLLOW UP CODE ENFORCE
| Date |
Description |
Inspector |
Results |
Comments |
| 01/20/2022 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
The electrical panels have all been pulled apart and cleaned and dried. The transformer have also been pulled apart and checked for water and all are OK. The locks were pulled off the disconnects and the panels were turned back on and all was working fine. Big Bear Electric LLC was the contractor doing the work. The sprinkler head is in the process of being replaced and working on changing all the heads in the room due to the age of the heads. At this time the case will be closed. Violation Abated, Close Case. RV. |
| 01/19/2022 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
Went back to the structure to check if the locks could be removed and the electrician was still checking the panels due to were wet. They were checking and drying the components in the panels. The sprinkler head was in the process of being replaced and were checking on changing all in the area due to the age of the heads. Will check in the morning tomorrow. RV. |