Inspection Status: Passed
Inspection History: BULD - Electrical Clearance
| Date |
Description |
Inspector |
Results |
Comments |
| 12/15/2022 |
BULD - Electrical Clearance |
|
Passed |
Approved, INCR clearance was called into TEP (power-kill) for unit #E, 4-pack panel |
| 12/15/2022 |
BULD - Electrical Clearance |
|
Passed |
Approved, INCR clearance was called into TEP (power-kill) for unit #F 4-pack panel |
| 12/15/2022 |
BULD - Electrical Clearance |
|
Passed |
Approved, INCR clearance was called into TEP (power-kill) for unit #G , 4-pack panel |
| 12/15/2022 |
BULD - Electrical Clearance |
|
Passed |
Approved, INCR clearance was called into TEP (power-kill) for unit #H, 4-pack panel |