Inspection Status: Partial Pass
Inspection History: COT - LCEL - Electrical Underground
| Date |
Description |
Inspector |
Results |
Comments |
| 01/06/2023 |
COT - LCEL - Electrical Underground |
|
Partial Pass |
PARTIAL- risers at pump 1 and 2, okay to backfill and for concrete placement |
| 01/11/2023 |
COT - LCEL - Electrical Underground |
|
Partial Pass |
Partial at pump #2, okay to backfill and concrete encase progress areas |
| 01/12/2023 |
COT - LCEL - Electrical Underground |
|
Passed |
Approved, okay to backfill and concrete encase all |
| 01/31/2023 |
COT - LCEL - Electrical Underground |
|
Partial Pass |
Approved 30’ underground, okay for concrete encasement |
| 03/27/2023 |
COT - LCEL - Electrical Underground |
|
Passed |
|