Inspection Status: Not Ready

Inspection History: COT - HCBU - Masonry Pregrout 

Date Description Inspector Results Comments
01/09/2024 COT - HCBU - Masonry Pregrout  Not Ready
01/10/2024 COT - HCBU - Masonry Pregrout  Partial Pass
01/12/2024 COT - HCBU - Masonry Pregrout  Partial Pass 1/12/24 2nd lift
01/17/2024 COT - HCBU - Masonry Pregrout  Partial Pass
01/24/2024 COT - HCBU - Masonry Pregrout  Partial Pass 12/14/23: 2 cells below grade full grout reinforcement per plan per detail S2.1
1/10/23 first lift ok for grout
1/12/24 2nd lift
1/17/24 3rd lift ok for grout
1/24/24: 4th and final lift ok for grout.
01/26/2024 COT - HCBU - Masonry Pregrout  Partial Pass 12/14/23: 2 cells below grade full grout reinforcement per plan per detail S2.1
1/10/23 first lift ok for grout
1/12/24 2nd lift
1/17/24 3rd lift ok for grout
1/24/24: 4th and final lift ok for grout.
1/26/24: 6 bump-outs per plan first lift ok to grout.
01/29/2024 COT - HCBU - Masonry Pregrout  Partial Pass
01/30/2024 COT - HCBU - Masonry Pregrout  Partial Pass
02/01/2024 COT - HCBU - Masonry Pregrout  Passed
12/14/2023 COT - HCBU - Masonry Pregrout  Partial Pass 12/14/23: 2 cells below grade full grout reinforcement per plan per detail S2.1