Inspection Status: Not Ready
Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Not Ready |
|
| 03/13/2023 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Re-inspection required |
Need fire blocking, hammer arrestors, bang plates, wire stapling, move and add outlets and switches, and DWV test. Potable lines ok. Insulate attic potable lines. |
| 07/22/2024 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Passed |
7/22/24 - Project complete. |
| 10/12/2023 |
COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. |
|
Passed |
Approved items addressed, okay to insulate and drywall progress areas |