Permit: T22CM01851

Parcel: 11903429A


Addresses:

3309 S 12TH AV

Inspection Status: Passed

Inspection History: COT - HCBU - Building Progress

Date Description Inspector Results Comments
01/17/2024 COT - HCBU - Building Progress Passed 12/12/23: Masonry walls at 8’ - 12’, North, East, West. Ok to place grout in progress areas. Next lift will be 5'8" (top out)
12/18/23 pre grout top out ok to place concrete
1/17/24: Electrical rough-In per plan ok to proceed. Drywall ok to be installed on ceiling.
11/15/2023 COT - HCBU - Building Progress Partial Pass Pre-slab area. Compacted, Ok to place concrete in progress area.
11/30/2023 COT - HCBU - Building Progress Partial Pass CMU walls at 0’ - 4’; grouted (East, North, West walls)
12/05/2023 COT - HCBU - Building Progress Partial Pass Masonry walls at 4’ - 8’, North, East, West. Ok to place grout in progress areas.
12/12/2023 COT - HCBU - Building Progress Partial Pass 12/12/23: Masonry walls at 8’ - 12’, North, East, West. Ok to place grout in progress areas. Next lift will be 5'8" (top out)
12/18/2023 COT - HCBU - Building Progress Partial Pass 12/18/23 pre grout top out ok to place concrete