Inspection Status: Not Ready
Inspection History: COT - HCBU - Stem Wall/Retaining Wall
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - HCBU - Stem Wall/Retaining Wall |
|
Not Ready |
|
| 01/04/2023 |
COT - HCBU - Stem Wall/Retaining Wall |
|
Partial Pass |
CMU masonry wall at loading dock; GL: H.2/14 -19; H.2/14.8; H.2/8.5. OK to place grout in progress areas. |
| 01/19/2023 |
COT - HCBU - Stem Wall/Retaining Wall |
|
Not Ready |
Contractor cancelled, will reschedule for 20 January. |
| 05/19/2023 |
COT - HCBU - Stem Wall/Retaining Wall |
|
Passed |
Retaining/site wall footing at Southwest area and West area: approximately 180 feet. Ok to place concrete in progress areas. |
| 11/15/2022 |
COT - HCBU - Stem Wall/Retaining Wall |
|
Partial Pass |
Loading dock area: retaining wall footings. Ok to place concrete in progress areas |