Inspection Status: Not Ready
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Not Ready |
|
| 10/20/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
ESTEVENS |
Partial Approval |
Entered by NGARCIA3 - Partial exterior footing only.
|
| 10/14/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
ESTEVENS |
Partial Approval |
Entered by NGARCIA3 - Partial. Per engineer, Galvan, no continuous rebar in footing at plumbing. |
| 10/28/2022 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Permit clean up, all footer inspections in passed status |