Inspection Status: Not Ready
Inspection History: COT - LCBU - Masonry Pregrout
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCBU - Masonry Pregrout |
|
Not Ready |
|
| 10/19/2022 |
COT - LCBU - Masonry Pregrout |
TGAUSP |
Partial Approval |
Entered by VVERA1 - PARTIAL for 4th lift (18’) at the front wall and columns are topped out (12’), okay to grout progress areas |
| 10/05/2022 |
COT - LCBU - Masonry Pregrout |
RCHANDLER |
Partial Approval |
Entered by VVERA1 - -PA: 3rd lift complete; top out for West, South, and East walls. Front wall and columns remain. |
| 09/20/2022 |
COT - LCBU - Masonry Pregrout |
RCHANDLER |
Partial Approval |
Entered by NGARCIA3 - Partial Approval: 2nd lift. |
| 08/23/2022 |
COT - LCBU - Masonry Pregrout |
RCHANDLER |
Partial Approval |
Entered by NGARCIA3 - Partial Approval: First lift. |
| 08/10/2022 |
COT - LCBU - Masonry Pregrout |
RCHANDLER |
Partial Approval |
Entered by VVERA1 - Partial Approval: CMU stem wall only. |
| 10/25/2022 |
COT - LCBU - Masonry Pregrout |
|
Passed |
|