Inspection Status: Not Ready
Inspection History: COT - LCPL - Plumbing Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
COT - LCPL - Plumbing Intermediate |
|
Not Ready |
|
| 01/04/2024 |
COT - LCPL - Plumbing Intermediate |
|
Passed |
|
| 03/27/2023 |
COT - LCPL - Plumbing Intermediate |
|
Partial Pass |
Plumbing underground for new addition. Waste and vent lines (1 1/2” - 3”). Ok to cover progress areas. |
| 07/26/2023 |
COT - LCPL - Plumbing Intermediate |
|
Partial Pass |
for all in wall and above ceiling except restrooms |
| 08/18/2023 |
COT - LCPL - Plumbing Intermediate |
|
Partial Pass |
in wall for restrooms complete OK to cover |
| 09/20/2023 |
COT - LCPL - Plumbing Intermediate |
|
Partial Pass |
Domestic wAter line from water,main to building, ok to set,meter. Four inch sewer lines from building to main,sewer junction. Ok to cover progress areas. |