Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - LCBU - Stem Wall/Retaining Wall
Permit Number - T21CM07719
Inspection Description - COT - LCBU - Stem Wall/Retaining Wall
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCBU - Stem Wall/Retaining Wall | Not Ready | ||
10/13/2022 | COT - LCBU - Stem Wall/Retaining Wall | JBURGE | Partial Approval | Entered by NGARCIA3 - Partial. North stem/retaining wall; vertical rebar for stem wall and vertical rebar for masonry wall. Ok to set forms and place concrete. Approximately 172 feet. 418 N 4TH AV |
10/13/2022 | COT - LCBU - Stem Wall/Retaining Wall | JBURGE | Partial Approval | Entered by NGARCIA3 - Partial. Stem wall at 418 N 4th. Portion of the expansion footings: approximately 172 ‘. |
10/07/2022 | COT - LCBU - Stem Wall/Retaining Wall | JBURGE | Partial Approval | Entered by RSALDAT1 - Partial. Stem wall footing at North wall GL: A - B |
10/07/2022 | COT - LCBU - Stem Wall/Retaining Wall | JBURGE | Not ready for Inspection | Entered by RSALDAT1 - Not ready. Contractor cancelled. |
01/11/2023 | COT - LCBU - Stem Wall/Retaining Wall | Partial Pass | Stem wall footing for West wall, change reflected on SK-2, dated 29 August 2022. Ok to place concrete in progress areas. | |
02/02/2023 | COT - LCBU - Stem Wall/Retaining Wall | Partial Pass | Stem wall footings at South wall area. Pier footings at West side of existing building. Ok to place concrete in progress areas. | |
02/08/2023 | COT - LCBU - Stem Wall/Retaining Wall | Partial Pass | South stem wall; first lift. Ok to place grout. | |
02/13/2023 | COT - LCBU - Stem Wall/Retaining Wall | Partial Pass | Stem wall (formed) at 44” AFFE, South wall. Ok to place concrete in progress areas. Two pier footings on west side of existing building. Ok to place concrete in progress areas. | |
02/21/2023 | COT - LCBU - Stem Wall/Retaining Wall | Partial Pass | South retaining wall at 4’ above finish floor. Ok to place grout in progress areas. | |
02/28/2023 | COT - LCBU - Stem Wall/Retaining Wall | Partial Pass | CMU stem wall (south wall), at 8’ - 12’. Ok to grout progress areas. Four column footings as per plan. Ok to place concrete in progress areas. | |
03/02/2023 | COT - LCBU - Stem Wall/Retaining Wall | Partial Pass | CMU retaining wall at 8’ - 12pm. Ok to place grout in progress areas. | |
03/06/2023 | COT - LCBU - Stem Wall/Retaining Wall | Partial Pass | CMU South wall at 12’ - 16’: bolts and hold downs are in place. Ok to grout progress areas. | |
03/08/2023 | COT - LCBU - Stem Wall/Retaining Wall | Partial Pass | Southwest retraining wall topped out at 16 feet. Ok to grout progress areas. | |
08/08/2023 | COT - LCBU - Stem Wall/Retaining Wall | Partial Pass | ||
10/23/2023 | COT - LCBU - Stem Wall/Retaining Wall | Passed | Ok to place concrete in footing areas. |