Inspection History Details
Inspection Status: Partial Pass
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/05/2025 | BULD - Electrical Clearance | Partial Pass | Partial pass. Inspection was for underground electric from pedestal location to new service panel. Okay to backfill progress areas. Shading is required. Will call clearance inspection at a later time. 6/5/2025 | |
| 06/23/2025 | BULD - Electrical Clearance | Passed | 6/23/25 TEP clearance: ECO |
|
| 12/23/2024 | BULD - Electrical Clearance | Not Ready | Contractor cancelled. | |
| 12/30/2024 | BULD - Electrical Clearance | Partial Pass | Ok to set meter. TEP needs to move power pole and set transformer before service can be applied. |