Inspection Status: Not Ready
Inspection History: COT - LCBU - Preslab
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCBU - Preslab |
|
Not Ready |
|
| 03/29/2022 |
COT - LCBU - Preslab |
TGAUSP |
Partial Approval |
Entered by NGARCIA3 - Partial for east end of building Gridline 9 to Gridline 13
|
| 08/17/2022 |
COT - LCBU - Preslab |
TGAUSP |
Approved |
Entered by VVERA1 - Approved, okay for concrete placement |
| 04/04/2022 |
COT - LCBU - Preslab |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - Partial GL 7-9 ok for concrete placement. |
| 03/29/2022 |
COT - LCBU - Preslab |
TGAUSP |
Partial Approval |
Entered by NGARCIA3 - - Partial for east end of building Gridline 9 to Gridline 13 |
| 01/20/2023 |
COT - LCBU - Preslab |
|
Passed |
|