Permit: T21CM04992

Parcel: 117073560


Addresses:

45 W LALO WY


Inspection Status: Partial Pass

Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.

Permit Number - T21CM04992

Inspection Description - COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.

Inspection Status - Partial Pass

Date Description Inspector Results Comments
01/12/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass Building progress only.
05/16/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass Inspection is for rebar in footings, ok to cover progress areas. Ensure electric ufer is properly installed.
06/05/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass Inspection is for north footings/rebar. Ok to place concrete in progress areas.
06/12/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass This inspection is for stem wall footings. Ok to place concrete in progress areas.
06/21/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass Inspection should read plumbing underground and sewer HCS Connection. Ok to cover,progress areas.
07/24/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass Inspection is for pre-slab. Ok to place concrete in progress areas.
08/22/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass
08/28/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass Level #2, West fire wall with Unit #49.
09/05/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass Interior fire walls at level #3 for units #45 and #48. Unit #48: CMU front wall at 24 feet; Ok to grout progress areas.
09/24/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass Interior framing system.