| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/05/2024 | COT - HCBU - Preslab | Partial Pass | 2/5/24: reinforcement per plan at Ramada columns ok to grout first lift at 4', ok to proceed | |
| 02/15/2024 | COT - HCBU - Preslab | Passed | 2/5/24: reinforcement per plan at Ramada columns ok to grout first lift at 4', ok to proceed 2/15/24: reinforcement per plan at Ramada columns ok to grout second lift Top out. |
|
| 07/10/2023 | COT - HCBU - Preslab | Partial Pass | The footer and the slab area has been approved for placement of concrete for the trash and closure on the site. Additional inspections Will be required for the structure in the following areas. Once the walls have been constructed up to the 4 foot level, internal grout will be required and a final inspection for the completion of the wall placement of the grout for the upper 2 feet will also be required. |