Inspection Status: Not Ready
Inspection History: COT - LCPL - Plumbing Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
COT - LCPL - Plumbing Intermediate |
|
Not Ready |
|
| 03/16/2023 |
COT - LCPL - Plumbing Intermediate |
|
Not Ready |
|
| 03/21/2023 |
COT - LCPL - Plumbing Intermediate |
|
Partial Pass |
see building progess |
| 03/30/2023 |
COT - LCPL - Plumbing Intermediate |
|
Not Ready |
|
| 04/06/2023 |
COT - LCPL - Plumbing Intermediate |
|
Partial Pass |
209-211-213/ 109-111-113 plumbing intermediate approved 4/6/2023 |
| 04/11/2023 |
COT - LCPL - Plumbing Intermediate |
|
Partial Pass |
109,111,113,209,211,213 ok to proceed |
| 04/14/2023 |
COT - LCPL - Plumbing Intermediate |
|
Partial Pass |
4-14-23: Units 109, 111, 113, 209, 211, and 213. |
| 04/28/2023 |
COT - LCPL - Plumbing Intermediate |
|
Passed |
4-28-23: Units 102-108, and 201-208. |
| 12/12/2022 |
COT - LCPL - Plumbing Intermediate |
|
Canceled |
wanted UG Plumbing, but not on permit. |