Inspection Status: Passed
Inspection History: COT - LCEL - Electrical Underground
| Date |
Description |
Inspector |
Results |
Comments |
| 12/29/2021 |
COT - LCEL - Electrical Underground |
DQUINN |
Approved |
Entered by VVERA1 - Ap
Underground conduits for parking canopies complete, with todays - bldg D to Can 3,
Can 3 to Can 2, and Can 3 to Can 1.
|
| 12/22/2021 |
COT - LCEL - Electrical Underground |
DQUINN |
Partial Approval |
Entered by VVERA1 - pa
Phase 1 - underground for canopy 4, to canopy 3, and then to the main panel on adjacent building, ok to backfill.
|
| 10/29/2021 |
COT - LCEL - Electrical Underground |
WGALLAGHER |
Cancelled |
Entered by NGARCIA3 - Inspection canceled by contractor
|
| 10/28/2021 |
COT - LCEL - Electrical Underground |
DQUINN |
Cancelled |
Entered by VVERA1 - ca
Per Isaiah |