Inspection Status: Continued
Inspection History: TDOT-EXCAV GENERAL INSPECTION
Permit Number - T20RW03489
Inspection Description - TDOT-EXCAV GENERAL INSPECTION
Inspection Status - Continued
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/05/2020 | TDOT-EXCAV GENERAL INSPECTION | Continued | Inspection of sidewalk subgrade and form work. | |
09/22/2020 | TDOT-EXCAV GENERAL INSPECTION | Continued | TRAFFIC CONTROL IS OK. FENCE STILL UP AROUND SITE | |
09/10/2020 | TDOT-EXCAV GENERAL INSPECTION | Continued | Reviewed the areas of asphalt to be replaced along the 3 entry areas. Contractor said that the cracked concrete will be replaced before end of work. | |
09/03/2020 | TDOT-EXCAV GENERAL INSPECTION | Continued | Inspected sidewalk area between middle drive and north. Subgrade, expansion joint and forms ready for pour. Notified contractor about the structural cracks in the north and south drives. |
|
08/26/2020 | TDOT-EXCAV GENERAL INSPECTION | Continued | Middle drive apron formed, ABC placed and compacted as well as the 6" expansion joint bmaterial placed. Ready for concrete. |
|
08/17/2020 | TDOT-EXCAV GENERAL INSPECTION | Continued | North entry apron poured. | |
08/14/2020 | TDOT-EXCAV GENERAL INSPECTION | Continued | North drive - ABC being graded. 6" expansion joint material installed. | |
08/12/2020 | TDOT-EXCAV GENERAL INSPECTION | Continued | ABC being placed at the 2 remaining entries. | |
07/31/2020 | TDOT-EXCAV GENERAL INSPECTION | Continued | Concrete apron slab poured. In process of finishing concrete. | |
07/30/2020 | TDOT-EXCAV GENERAL INSPECTION | Continued | South drive apron ready for concrete placement. Curbs completed, ABC subgrade compacted and 4" expansion joint material on site, told contractor that need 6" expansion Joint material at the 6" concrete apron slab. | |
07/24/2020 | TDOT-EXCAV GENERAL INSPECTION | Continued | Existing curb at new south entry removed. | |
07/20/2020 | TDOT-EXCAV GENERAL INSPECTION | Continued | No additional work performed. | |
07/16/2020 | TDOT-EXCAV GENERAL INSPECTION | Continued | Clearing completed. Short section of old sidewalk removed. Fiber optic boxes still need investagation as to ability to move units. Moved construction fence to roadway with barricades. | |
07/02/2020 | TDOT-EXCAV GENERAL INSPECTION | Continued | Precon at 7:30. 2 phases due to access to construction site. 2 fiberoptic cable boxes in sidewalk area. Will research to see if they can be moved. |