Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
Permit Number - T20CM07068
Inspection Description - REINFORCED MASONRY PRE-GROUT
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/17/2021 | REINFORCED MASONRY PRE-GROUT | Approved | ||
| 05/14/2021 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | ||
| 05/13/2021 | REINFORCED MASONRY PRE-GROUT | Cancelled | No response from contact Inspection canceled |
|
| 03/26/2021 | REINFORCED MASONRY PRE-GROUT | Partial Approval | Partial. Two entry columns, first lift. | |
| 03/24/2021 | REINFORCED MASONRY PRE-GROUT | Partial Approval | Partial. West retaining wall,running north to south and ending at 45 degree turn east,top out. | |
| 03/02/2021 | REINFORCED MASONRY PRE-GROUT | Cancelled | CANCELLED | |
| 03/01/2021 | REINFORCED MASONRY PRE-GROUT | Partial Approval | PARTIAL ALL EXTERIOR GYM WALL, TOP-OUT | |
| 02/26/2021 | REINFORCED MASONRY PRE-GROUT | Partial Approval | PARTIAL - North east and west walls of gymnasium OK to grout to 28 feet | |
| 02/25/2021 | REINFORCED MASONRY PRE-GROUT | Partial Approval | Partial. East wall ( SE Of gym)to control joint at 28’; Whole West wall to 24’. | |
| 02/24/2021 | REINFORCED MASONRY PRE-GROUT | Partial Approval | PARTIAL NORTH AND SOUTH GYM WALLS TO 24 FEET, ELEVATOR TO 28 FEET | |
| 02/22/2021 | REINFORCED MASONRY PRE-GROUT | Partial Approval | PARTIAL - NORTH AND WEST GYM WALLS TO 20 FEET, ELEVATOR SHAFT TO 12 FEET | |
| 02/19/2021 | REINFORCED MASONRY PRE-GROUT | Partial Approval | SOUTH AND EAST WALLS TO 20', NORTH AND WEST WALLS TO 16' | |
| 02/18/2021 | REINFORCED MASONRY PRE-GROUT | Partial Approval | APPROVED FOR THE EAST AND SOUTH WALLS AT TYE 16’ HEIGHT ONLY. ALL CONTROL JOINTS,REBAR AS PER PLANS. | |
| 02/17/2021 | REINFORCED MASONRY PRE-GROUT | Partial Approval | Partial. West and North walls to 12’. | |
| 02/16/2021 | REINFORCED MASONRY PRE-GROUT | Partial Approval | PARTIAL SOUTH WALL TO 12 FEET, EAST AND WEST WALL TO 8 FEET | |
| 02/15/2021 | REINFORCED MASONRY PRE-GROUT | Partial Approval | NORTH AND SOUTH WALLS OF GYMNASIUM AND ELEVATOR SHAFT OK TO GROUT TO 8'. | |
| 02/13/2021 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 4' LIFT AT GYMNASIUM AND ELEVATOR SHAFT OK TO GROUT | |
| 02/04/2021 | REINFORCED MASONRY PRE-GROUT | Partial Approval | PARTIAL APPROVAL FOR ELEVATOR FIRST LIFT FROM SUB FLOOR TO FINISH FLOOR HEIGHT | |
| 02/03/2021 | REINFORCED MASONRY PRE-GROUT | Cancelled | CANCELLED NOT READY |