Permit: T20CM07068

Parcel: 13633148C

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T20CM07068

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
07/02/2021 EXCAVATION/LAYOUT REBAR & ZON Approved
06/02/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PA. Four light pole bases; one on West side, two on South side, and one on East side.
03/22/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Next four light pole bases complete (15 total). Ok to pour.
03/19/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Eleven light pole bases complete, ok to pour.
03/17/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. South retaining wall footing, ok to pour.
03/15/2021 EXCAVATION/LAYOUT REBAR & ZON Cancelled CANCELLED NOT READY
02/25/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Remainder of West wall footing.
02/17/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. West wall footing, NE of retention basin.
02/16/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PARTIAL NORTHEAST TO SOUTHWEST RETAINING WALL FOOTING OK TO POUR
02/01/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PARTIAL INTERIOR/EXTERIOR FOOTERS