Permit: T20CM04050

Parcel: 140420120


Addresses:

7073 S PLUMER AV


Inspection Status: Approved

Inspection History: ELECTRIC - UNDERGROUND

Permit Number - T20CM04050

Inspection Description - ELECTRIC - UNDERGROUND

Inspection Status - Approved

Date Description Inspector Results Comments
08/26/2021 ELECTRIC - UNDERGROUND Approved Approved
06/17/2021 ELECTRIC - UNDERGROUND Partial Approval Partial no inspection required today.
06/16/2021 ELECTRIC - UNDERGROUND Partial Approval PARTIAL, AOA gate conduits complete, S duct bank complete and ok for concrete.
06/03/2021 ELECTRIC - UNDERGROUND Partial Approval Partial, Completion of Duct bank F ok for concrete placement.
06/02/2021 ELECTRIC - UNDERGROUND Partial Approval
05/26/2021 ELECTRIC - UNDERGROUND Partial Approval INSPECTION PLACED IN AP BY INSPECTOR RELEFANTE ON 05/26/21. INSPECTION PLACED IN PA BY INSPECTOR DMUNIZ ON 06/02/21.
05/20/2021 ELECTRIC - UNDERGROUND Partial Approval Partial. Ground rods and grounding electrode conductor tied together at generator and PDC area.
04/27/2021 ELECTRIC - UNDERGROUND Partial Approval Partial, conduits installed from tank 1 to tank 2 for Future MOV controls ok to backfill progress.
04/23/2021 ELECTRIC - UNDERGROUND Partial Approval Partial, Installation of Duct bank J to Tank 1
Ok for concrete placement.
04/20/2021 ELECTRIC - UNDERGROUND Partial Approval Partial, continuation of Duct bank F to Tunnel ok to backfill.
04/19/2021 ELECTRIC - UNDERGROUND Partial Approval Partial, Inspection of partial Installation of Duct bank F from off loading station towards PDC ok for concrete encasement.
03/31/2021 ELECTRIC - UNDERGROUND Partial Approval Partial, Duct bank B installed from PDC to Generator location ok for concrete placement.
03/17/2021 ELECTRIC - UNDERGROUND Partial Approval Partial, duct bank and Underground conduit progress 50’ from manhole to tunnel ok to place concrete.
03/16/2021 ELECTRIC - UNDERGROUND Partial Approval Partial, Duct Banks L,N,P ok for concrete placement.
03/04/2021 ELECTRIC - UNDERGROUND Partial Approval Partial, conduits installed through duct banks and continued to South vaults.
03/03/2021 ELECTRIC - UNDERGROUND Partial Approval PARTIAL NO INSPECTION TODAY SEE PREVIOUS NOTES
03/02/2021 ELECTRIC - UNDERGROUND Partial Approval Partial, conduit for site lighting ok to backfill, South Duct bank progress towards vaults ok to proceed.
02/18/2021 ELECTRIC - UNDERGROUND Partial Approval Partial. From duct bank A, power distribution center to the TEP transformer. From the north parking lot to an existing electrical lighting box. From duck bank E, Power distribution center to the tank farm, offshoots to tank one, offshoots to tank two. From duct bank G to off loading pad and operations building. From duct bank D, to Power Distribution Center, to pump pad. From the power distribution center to the variable frequency drive.
02/10/2021 ELECTRIC - UNDERGROUND Partial Approval Partial approval duct bank G from PDC to OPS building ok for concrete placement. Partial approval duct bank from point 18 to other side of OPS building ok for concrete. Partial approval duct bank E from PDC 60’ west ok for concrete
02/03/2021 ELECTRIC - UNDERGROUND Partial Approval Partial. From main power distribution center to all locations on pump pad. From main distribution center under off loading pad to ops building.