Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - UNDERGROUND
Permit Number - T20CM04050
Inspection Description - ELECTRIC - UNDERGROUND
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/26/2021 | ELECTRIC - UNDERGROUND | Approved | Approved | |
06/17/2021 | ELECTRIC - UNDERGROUND | Partial Approval | Partial no inspection required today. | |
06/16/2021 | ELECTRIC - UNDERGROUND | Partial Approval | PARTIAL, AOA gate conduits complete, S duct bank complete and ok for concrete. | |
06/03/2021 | ELECTRIC - UNDERGROUND | Partial Approval | Partial, Completion of Duct bank F ok for concrete placement. | |
06/02/2021 | ELECTRIC - UNDERGROUND | Partial Approval | ||
05/26/2021 | ELECTRIC - UNDERGROUND | Partial Approval | INSPECTION PLACED IN AP BY INSPECTOR RELEFANTE ON 05/26/21. INSPECTION PLACED IN PA BY INSPECTOR DMUNIZ ON 06/02/21. | |
05/20/2021 | ELECTRIC - UNDERGROUND | Partial Approval | Partial. Ground rods and grounding electrode conductor tied together at generator and PDC area. | |
04/27/2021 | ELECTRIC - UNDERGROUND | Partial Approval | Partial, conduits installed from tank 1 to tank 2 for Future MOV controls ok to backfill progress. | |
04/23/2021 | ELECTRIC - UNDERGROUND | Partial Approval | Partial, Installation of Duct bank J to Tank 1 Ok for concrete placement. |
|
04/20/2021 | ELECTRIC - UNDERGROUND | Partial Approval | Partial, continuation of Duct bank F to Tunnel ok to backfill. | |
04/19/2021 | ELECTRIC - UNDERGROUND | Partial Approval | Partial, Inspection of partial Installation of Duct bank F from off loading station towards PDC ok for concrete encasement. | |
03/31/2021 | ELECTRIC - UNDERGROUND | Partial Approval | Partial, Duct bank B installed from PDC to Generator location ok for concrete placement. | |
03/17/2021 | ELECTRIC - UNDERGROUND | Partial Approval | Partial, duct bank and Underground conduit progress 50’ from manhole to tunnel ok to place concrete. | |
03/16/2021 | ELECTRIC - UNDERGROUND | Partial Approval | Partial, Duct Banks L,N,P ok for concrete placement. | |
03/04/2021 | ELECTRIC - UNDERGROUND | Partial Approval | Partial, conduits installed through duct banks and continued to South vaults. | |
03/03/2021 | ELECTRIC - UNDERGROUND | Partial Approval | PARTIAL NO INSPECTION TODAY SEE PREVIOUS NOTES | |
03/02/2021 | ELECTRIC - UNDERGROUND | Partial Approval | Partial, conduit for site lighting ok to backfill, South Duct bank progress towards vaults ok to proceed. | |
02/18/2021 | ELECTRIC - UNDERGROUND | Partial Approval | Partial. From duct bank A, power distribution center to the TEP transformer. From the north parking lot to an existing electrical lighting box. From duck bank E, Power distribution center to the tank farm, offshoots to tank one, offshoots to tank two. From duct bank G to off loading pad and operations building. From duct bank D, to Power Distribution Center, to pump pad. From the power distribution center to the variable frequency drive. | |
02/10/2021 | ELECTRIC - UNDERGROUND | Partial Approval | Partial approval duct bank G from PDC to OPS building ok for concrete placement. Partial approval duct bank from point 18 to other side of OPS building ok for concrete. Partial approval duct bank E from PDC 60’ west ok for concrete | |
02/03/2021 | ELECTRIC - UNDERGROUND | Partial Approval | Partial. From main power distribution center to all locations on pump pad. From main distribution center under off loading pad to ops building. |