Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - UFER
Permit Number - T20CM04050
Inspection Description - ELECTRIC - UFER
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/26/2021 | ELECTRIC - UFER | Approved | Approved | |
06/02/2021 | ELECTRIC - UFER | Partial Approval | ||
06/02/2021 | ELECTRIC - UFER | Partial Approval | partial, conduit laterals from duct bank F ok to shade to form bulk head. | |
05/26/2021 | ELECTRIC - UFER | Partial Approval | INSPECTION PLACED IN AP BY INSPECTOR RELEFANTE ON 05/26/21. INSPECTION PLACED IN PA BY INSPECTOR DMUNIZ ON 06/02/21. | |
05/12/2021 | ELECTRIC - UFER | Partial Approval | Partial, Uffer attachment and ground ring with rods installed for Generator. | |
03/31/2021 | ELECTRIC - UFER | Partial Approval | Partial, EGC installed through Duct bank B from PDC to Generator location ok for concrete placement. | |
03/17/2021 | ELECTRIC - UFER | Partial Approval | Partial, Grounding Conductor installed through duct bank and underground conduits from manhole to tunnel. | |
03/16/2021 | ELECTRIC - UFER | Partial Approval | Partial, Inspection of Ground Rods and EGC for tank 2, 3 & duct banks L,N,P. Ground Installed in footing for PDC. | |
03/04/2021 | ELECTRIC - UFER | Partial Approval | Partial, EGC installed with duct banks and terminated @ vaults. |