Permit: T20CM04050

Parcel: 140420120


Addresses:

7073 S PLUMER AV


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T20CM04050

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
01/24/2022 EXCAVATION/LAYOUT REBAR & ZON Approved Approved
10/01/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval partial, containment dike wall progress ok for concrete placement
09/24/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PARTIAL, progress for containment dike wall ok to proceed.
09/21/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PARTIAL, Progress for containment dike wall ok for concrete placement.
09/17/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, containment walls ok for concrete placement.
09/14/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, progress for containment wall on east side ok for concrete placement at progress areas.
08/31/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval partial, Containment dike walls on west side of tanks 1,2&3, containment footings on east side of tanks 1,2,3 all ok for concrete placement in progress areas.
08/19/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, continued footing for containment walls on west side of tank 1 & 2 including interior containment footings ok for concrete placement.
08/11/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, Inspection for containment wall footings South/West of Tank #3 ok for concrete placement in completed areas.
07/26/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, inspection for following locations complete. Hydra cart stand, off load station, & 2 light pole bases all ok for concrete placement.
07/23/2021 EXCAVATION/LAYOUT REBAR & ZON Cancelled CANCELLED BY CONTRACTOR
07/20/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, Inspection for continued driveway rebar and wire mesh from north entrance to office building. Ok for concrete placement.
06/23/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, hydra cart footings, lighting poles in front office building. & North East slab ok for concrete placement.
06/22/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial , Northwest lighting caisson inspected, install conduit sweep and Ground connection.
06/17/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, Inspection of Pedestal columns for off loading station ok for concrete placement.
06/10/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, 6 housekeeping pads,& truck off loading footings ok for concrete placement.
06/02/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, Product recovery tank location and pump pad ok for concrete placement.
05/27/2021 EXCAVATION/LAYOUT REBAR & ZON Cancelled CANCELLED THERE WAS NO PHONE NUMBER LEFT ON MESSAGE FOR POINT OF CONTACT
05/26/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval INSPECTION PLACED IN AP BY INSPECTOR RELEFANTE ON 05/26/21. INSPECTION PLACED IN PA BY INSPECTOR DMUNIZ 06/02/21
05/24/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, North pump pad inspected and ok for concrete placement. (2 of 3)
05/20/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Recovery tanks area for the pump pad and pre-slab area for pump number one.
05/12/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, Foundation for Generator ok for concrete placement.
04/28/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, 3 Footings for pump pads ok to place concrete.
04/23/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, installation of 2 footings for PDC ok for concrete placement.
04/12/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, Grade beam footings for Operations building ok for concrete.
04/08/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, Footing and slab for tank 1 ok for concrete placement.
03/24/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, Footings for Operations building ok for concrete placement.
03/18/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, no inspection today see previous notes.
03/16/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, spread Footings and Stems for PDC building ok for concrete on completed 6 footings.
03/05/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, Re-bar re-enforcement for foundation footing on Tank #2 ok for concrete placement.
03/04/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial, Rebar casings for duct banks ok for concrete placement ok on south end progress.
02/22/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval APPROVED FOR TANK #3