Inspection Status: Passed
Inspection History: COT - LCPL - Sewer
| Date |
Description |
Inspector |
Results |
Comments |
| 03/02/2022 |
COT - LCPL - Sewer |
TGAUSP |
Approved |
Entered by NGARCIA3 - Approved, Building 2 |
| 02/11/2022 |
COT - LCPL - Sewer |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - Partial, UNITS 2106-2112 INSTALLED AND TESTED OK TO BACKFILL.
|
| 01/12/2022 |
COT - LCPL - Sewer |
TGAUSP |
Partial Approval |
Entered by RSALDAT1 - Partial approval for Building 2, units 1113 - 1119
|
| 04/19/2021 |
COT - LCPL - Sewer |
DMUNIZ |
Approved |
Entered by VLEON1 - Approved, Main Line connections and Vertical risers with tracer lines installed & ok to backfill progress.
|
| 03/30/2021 |
COT - LCPL - Sewer |
DMUNIZ |
Partial Approval |
Entered by RSALDAT1 - Partial, Inspection for Private sewer on Bldg 1 ok to backfill progress.
|