Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
| Date |
Description |
Inspector |
Results |
Comments |
| 11/17/2021 |
BUILDING PRE-SLAB |
|
Approved |
Approved. North side landings and stairs. Ok to place concrete in progress areas. |
| 11/30/2020 |
BUILDING PRE-SLAB |
|
Partial Approval |
Partial. Slab pour 3 of 3. North east side. |
| 11/16/2020 |
BUILDING PRE-SLAB |
|
Partial Approval |
Partial, middle third of slab west of elevator shaft ok for concrete placement. |
| 11/03/2020 |
BUILDING PRE-SLAB |
|
Partial Approval |
Partial, East side Of Building 3 slab ok for concrete placement. |