Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T20CM00360

Parcel: 117062070


Addresses:

127 S 5TH AV

Inspection Status: Partial Approval

Inspection History: BUILDING - FINAL

Date Description Inspector Results Comments
06/15/2021 BUILDING - FINAL Partial Approval Partial. Ok to move in equipment for staff and allow staff in for training. Ok to make application for TCO on 1June 2021 for occupancy of room units 202, 204, 207 304, 306, 402, 406. Pending Fire Finals.
06/10/2021 BUILDING - FINAL Partial Approval INSPECTOR JB APPROVED ON 06/10/21. INSPECTOR JB PLACED INSPECTION ITEM IN PA TODAY 06/15/21.
06/01/2021 BUILDING - FINAL Partial Approval Partial. Ok to make application for Temporary Certificate of Occupancy for Room Units 202; 204; 207; 306; 406; 402; to occupy.
05/28/2021 BUILDING - FINAL Cancelled CANCELLED BY WESLEY
05/27/2021 BUILDING - FINAL Partial Approval REVIEW OF AIR BALANCE REPORT COMPLETED
05/27/2021 BUILDING - FINAL Partial Approval