Inspection Status: Approved
Inspection History: FRAMING
| Date |
Description |
Inspector |
Results |
Comments |
| 05/20/2021 |
FRAMING |
|
Approved |
|
| 04/16/2021 |
FRAMING |
|
Cancelled |
CANCELLED BY CONTRACTOR |
| 03/03/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #1; Lounge/Lobby areas and restrooms. Ok to insulate and cover walls. |
| 02/24/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #1; Lobby areas and restrooms. Ok to insulate and cover walls |
| 02/12/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #7 Corridor, walls and ceilings. Ok to insulate and cover walls. |
| 02/03/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #7; Room Units 710 - 174. Ok to insulate and cover walls. |
| 01/25/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #7; Room Units 703; 704. Ok to insulate and cover walls. |
| 01/22/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #7; Room Units 705; 706; 707; 708; 709. Ok to insulate and cover walls |
| 01/13/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #6; Room Units 601; 602; 603; 604; 616. Ok to cover walls. |
| 01/11/2021 |
FRAMING |
|
Partial Approval |
Partial. Level #6 Room Units 601; 602; 603; 616 |
| 01/05/2021 |
FRAMING |
|
Not ready for Inspection |
Not ready. Electric not ready. |
| 12/31/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #6; Room Units 605; 606; 609; 610; 613; 614; 615. Ok to insulate and cover walls. |
| 12/16/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #5; Room Units 501; 502; 503; 504; 505; 515. Ok to insulate and cover walls. |
| 12/14/2020 |
FRAMING |
|
Partial Approval |
PARTIAL |
| 12/11/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #5; Room Units 507; 508; 509; 510; 511; 512; 513. Ok to insulate and cover walls. |
| 11/25/2020 |
FRAMING |
|
Partial Approval |
Partial. Level 4, units 403 thru 409. |
| 11/24/2020 |
FRAMING |
|
Partial Approval |
Partial. Level 4, units 401 through 416. |
| 11/13/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #2; Room Units 201-216. Ok to insulate and cover walls. |
| 11/12/2020 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled will reschedule for 13 November. |
| 11/02/2020 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled |
| 10/30/2020 |
FRAMING |
|
Not ready for Inspection |
Not ready. Contractor cancelled, will reschedule for 3 November. |
| 09/23/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #4; 8 each duct shafts in East and Central corridor areas. Ok to cover shafts. |
| 09/21/2020 |
FRAMING |
|
Partial Approval |
Partial. Level #3; rooms and corridors except for East section of rooms. |
| 09/16/2020 |
FRAMING |
|
Not ready for Inspection |
Not ready. East portion of Level #3 is not complete. |