Permit: T20CM00360

Parcel: 117062070


Addresses:

127 S 5TH AV

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
05/20/2021 EXCAVATION/LAYOUT REBAR & ZON Approved
04/14/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Six each caisson footings and column beams at 9’4”. Ok to place concrete in progress areas.
09/14/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval . Partial. Level #7 West; Shear wall #1 at GL: A.5-B/2; Elevator Walls at GL:A-A.75/3.5-3.9. Columns at GL: A/1; A/2; A/3; A/4.4; B/4.4; B/1; B/3. Ok to place concrete in progress areas.
09/09/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Level #6 East; Columns at GL: D/2; D/3; D/4; E/1; E/2; E/3;
E/4. Ok to set forms and place concrete in progress areas.
09/03/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Not ready. Will inspect after slab pour.
09/01/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Level #5 East; 8 columns. Ok to set forms and place concrete in progress areas.
08/28/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Level #6 West: Shear wall #1 at GL: A.5-B/2; Elevator walls at GL: 3.4-4/A; 3.5/A-B; A.5/3.5-4; 4/A-B. Columns at GL: A/4.4; 3/A; B/4.4; B/4; B/3; C/4; C/3; B/3.5. Ok to place concrete in progress areas.
08/25/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Level #4 East shear wall. Ok to place concrete.
08/24/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Level #4 East, eight columns. Ok to set forms and place concrete.
08/21/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval . Partial. Retaining wall footing at South to Southeast property, approximately 75 feet. Ok to place concrete in progress areas.
08/19/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. West slab at Level #4 at GL: A-D/1-6. Columns at GL: A/1; B/1; C/1; C/2; C/3; C/4; B/4. Shear wall #1 at GL: A.5-B/2. Elevator walls at GL: A-B/3.5; A/3.5-4; A.5/3.5-4. Ok to place concrete in progress areas.
08/17/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Level 3 East columns at GL: F/1; F/2; F/3; F/4; E/4; G/3; G/4. Shear wall at GL: G/1-4.4. Ok to place concrete in progress areas.
08/11/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Level #3 West, Columns at GL: B/1; B/3; B/4; B/4.4; C/1; C/2; C/3; C/4. Elevator walls at GL: A-A.5/3.9-4. Ok to place concrete in progress areas.
07/31/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Level #2; Elevator shaft walls at GL: A-A.75/3.75; A/3.75-4; A.75/3.75-4. Pk to place concrete in progress area.
07/29/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Not ready. Elevator area rebar for walls not ready for inspection. Will reschedule for 30 July afternoon.
07/16/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Column footings at GL: CC1-F10 at F/3; CC1-F8 at G/3.
07/15/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Not ready. Contractor cancelled.
07/13/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Information for masonry placement at retaining walls.
07/10/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Stairwell footings at GL: A/4.4-5; 5/A-B; A.75/4.4-5; A/4.4-5. Retaining wall footing at GL: H/2-5.5. Ok to place concrete in progress areas.
07/09/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Not ready. Contractor cancelled, will reschedule for 10 July.
07/08/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Stem wall at GL: 1/A-B. Shear wall #1 at GL: 2/A.5-A.75; Shear wall #3 at GL: A-A.75/3.75; Shear wall #4 at GL: A/3.9-4; Shear wall #5 at GL: A.75/3.9-4; Shear wall #6 at GL: 4/A-A.75. Ok to place concrete in progress areas.
07/07/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Columns at GL: D/1; E/1; F/1; F/2; F/3; D/3.9; E/2; E/3. Ok to set forms and place concrete.
07/06/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Columns at GL: A/1; B/1; C/1; C/2; B/4; D/2; D/4. Ok to set forms and place concrete in progress areas.
07/02/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Wall footing at GL: 1/B.5-F.5. Columns: CC1-F7 at C/1: D/1; E/1; CC1-F9 at GL: F/2; F/3. Ok to place concrete in progress areas.
07/01/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Shear wall #6 at GL: 4/A-B; Column footing at GL: G/3 (CC1-F8); trash enclosure footings at GL: G-H/2.75-3.8. Ok to place concrete in progress.
06/30/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Double mat column footings at GL: B/3 (CC1-F10); B/4 (CC1-F7): Ok to place concrete in progress areas.
06/29/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Column footings at GL: G/1; G/2.5. Shear walls at GL: Shear wall #4 at 3.9-4/A; #5 at A.5/3.9-4. Ok to set forms and place concrete in progress areas.
06/26/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Not ready. Contractor cancelled. Will reschedule for 29 June.
06/25/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Stairwell footing at GL: A.2-B/1.5-2.5. Column footings at GL: A/1; B/1; 3/A. Wall footing at GL: A/1-3. Ok to place concrete in progress areas.
06/24/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Column footings at GL: 3.9/C; 3.9/D; 3.9/E; 3/C; 3/D; 3/E. North CMU retaining wall, North of GL: 1. Ok to place concrete in progress areas.
06/23/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Elevator pit at GL: 3.9-4.4/A-A.5. Ok to place concrete in progress area.
06/22/2020 EXCAVATION/LAYOUT REBAR & ZON Cancelled Canceled by contractor.
06/04/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Geo-pier information. Piers and compaction to be inspected by special inspector.