Inspection Status: Approved
Inspection History: PLUMBING - ABOVE CEILING
| Date |
Description |
Inspector |
Results |
Comments |
| 06/04/2021 |
PLUMBING - ABOVE CEILING |
|
Approved |
|
| 04/09/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
1044, 1036, 2036, 3036, 4036. Partial. Cowboys corridor. Storage rooms 408 B,C,D,&E. |
| 04/01/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
PARTIAL CARDINAL SECTION CORRIDOR |
| 03/24/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
1044, 1036, 2036, 3036, 4036. Partial. Cardinals/Green Bay section. Corredor area |
| 03/05/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
PARTIAL BUILDING 2 LEVEL 4 UNITS 2425 THRU 2437 |
| 01/13/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial. Green Bay section. Level one. Breezeway section |
| 01/13/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial. Cardinals section. Level four. Plumbing run through attic, units 2403 through 2406. |
| 01/11/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial. Green Bay section. Level 4. Units 2401, 2402. |
| 12/03/2020 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial. The breezeway between Green Bay and Cardinals sections. |
| 11/04/2020 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial. Southwest corner breezeway. |