Permit: T20CM00312

Parcel: 12513068A

Inspection Status: Approved

Inspection History: BUILDING ABOVE CEILING

Date Description Inspector Results Comments
08/16/2022 BUILDING ABOVE CEILING Approved Approved
04/09/2021 BUILDING ABOVE CEILING Partial Approval 1044, 1036, 2036, 3036, 4036. Partial. Cowboys corridor. Storage rooms 408 B,C,D,&E.
04/01/2021 BUILDING ABOVE CEILING Partial Approval PARTIAL CARDINAL SECTION CORRIDOR
03/24/2021 BUILDING ABOVE CEILING Partial Approval 1044, 1036, 2036, 3036, 4036. Partial. Cardinals/Green Bay section. Corredor area
03/11/2021 BUILDING ABOVE CEILING Partial Approval Partial. Level #3; Trash Room #315; Staff storage room #314. Ok to cover ceilings.
01/21/2021 BUILDING ABOVE CEILING Partial Approval Partial. Building #2; Cardinal Section Room Units 2407; 2408; 2409; 2410; 2411; 2412. Ok to sheet rock ceilings and top out areas of bathrooms.
01/13/2021 BUILDING ABOVE CEILING Partial Approval Partial. Green Bay section. Level one. Breezeway section
01/08/2021 BUILDING ABOVE CEILING Partial Approval Partial. Building number two. Green Bay section. Level four. Units 2401, 2402
12/03/2020 BUILDING ABOVE CEILING Partial Approval Partial. The breezeway between Green Bay and Cardinals sections.
11/04/2020 BUILDING ABOVE CEILING Partial Approval Partial. Southwest corner breezeway.