Permit: T20CM00312

Parcel: 12513068A

Inspection Status: Approved

Inspection History: FRAMING

Date Description Inspector Results Comments
09/02/2022 FRAMING Approved
06/17/2021 FRAMING Partial Approval Partial. Southeast stairwell
06/14/2021 FRAMING Partial Approval Partial. Cowboys section. Level four. Corridor.
06/04/2021 FRAMING Approved
04/23/2021 FRAMING Partial Approval Partial. Level five. Area 500 and stairwell 501.
04/20/2021 FRAMING Partial Approval PARTIAL LEVEL 4 BRONCO SECTION UNITS 2433 THROUGH 2437
04/19/2021 FRAMING Partial Approval PARTIAL LEVEL 4 UNITS 2425 THRU 2432
04/08/2021 FRAMING Partial Approval PARTIAL LEVEL 4 STORAGE ROOMS, UNITS 408 B, C, D, E
04/01/2021 FRAMING Partial Approval PARTIAL UNIT NUMBER 2424
03/31/2021 FRAMING Partial Approval 1044, 2035, 1035, 3035, 4035. Partial. Cowboys section. Units 2421, 2422, 2423.
03/25/2021 FRAMING Partial Approval PARTIAL UNITS 2417, 2418, 2419, 2420
03/25/2021 FRAMING Partial Approval PARTIAL COORIDOR IN COWBOYS SECTION
03/10/2021 FRAMING Partial Approval PARTIAL UNITS 2415 AND 2416
03/08/2021 FRAMING Partial Approval PARTIAL UNIT #2414
03/05/2021 FRAMING Partial Approval PARTIAL BUILDING 2, LEVEL 4, CARDINAL SECTION UNIT 2413
03/03/2021 FRAMING Partial Approval Partial. Building #1; Green Bay Room Unit #2401; Shear walls Level #4. Building #2; Level #4; Cardinals area Room Units 2409-2412.
02/26/2021 FRAMING Partial Approval Partial. Level three Cowboys section. Units 2331 and 2332.
02/26/2021 FRAMING Partial Approval Partial. Cardinal section. Level four. Units 2405, 2406, 2407, 2408.
02/25/2021 FRAMING Partial Approval Green Bay/Cardinals section. level 4. Units 2401, 2402, 2403, 2404.
02/24/2021 FRAMING Partial Approval Partial. Units 2417 and 2418. This is for sheer wall installation only.
02/17/2021 FRAMING Partial Approval Partial. Green Bay/Cardinals section. 2401 through 2416. OK to insulate party wall and Corredor walls only.
01/26/2021 FRAMING Partial Approval PARTIAL LEVEL #1 DENVER SECTION CORRIDOR WALLS FROM ELEVATOR TO EXPANTION JOINT OK TO INSULATE AND COVER WALLS
01/15/2021 FRAMING Partial Approval PARTIAL GREEN BAY SECTION NORTH WEST STARIWELL
12/01/2020 FRAMING Not ready for Inspection Not ready.
10/23/2020 FRAMING Partial Approval Partial. Level one, trash chute area.
10/16/2020 FRAMING Partial Approval Partial. Arizona Cardinals section, Level 4, exterior densglass, floor and roof decks.
09/28/2020 FRAMING Not ready for Inspection Not ready, not complete.
08/27/2020 FRAMING Partial Approval Partial. Exterior framing on levels 2&3 on Cardinal section of building.
08/21/2020 FRAMING Not ready for Inspection Not ready, not complete
08/19/2020 FRAMING Partial Approval Partial. This inspection was performed on 18 August.
08/18/2020 FRAMING Partial Approval Partial. Building #1; Levels #3; 4; parapet and roof area. Ok to cover progress areas.
08/14/2020 FRAMING Not ready for Inspection Not ready. Contractor cancelled.
08/10/2020 FRAMING Partial Approval Partial. Level 1, installed fire foam sealant around the top edge of fire walls. Ok to drywall the top around the sealant.
08/04/2020 FRAMING Not ready for Inspection Not ready, not complete.
05/13/2020 FRAMING Partial Approval Partial. Footings on gridlines 14-JJ, 16-JJ, 20-KK. Columns on gridlines 18-FF, 18-HH, 16-HH, 16-KK, 14-KK, 14-MM