Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 01/24/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
First asphalt patch was not accepted. Eagle rock milled asphalt to 3 inches below grade and reinstalled new asphalt. This patch was accepted 13x28. The backfill was done with all slurry. No issues |
| 01/09/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
SW gas installing new gas line from the middle of Cushing to property line. Eagle rock performed the excavation to the site. SW gas on site as a partnering issue. They were asked to be completed prior to the gem show with all repairs. SW gas will be completed bt the end of the week |