Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 06/07/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Last driveway completed. |
| 06/06/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Contractor removed affected driveway apron and is pouring concrete. Base and forms OK. |
| 06/04/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
No change. Called contractor - he will go che ck it out and correct all befor permit expires. |
| 05/15/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Only 1 private drive apron needs repair. |
| 04/23/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
7 street crossings with roadway repaired. Gas line completed. 2 concrete driveways crossed and used cold patch for temp. repair. 2 areas in Flower St. have cold patch with 1 saw cut. Contractor not completed. |
| 04/10/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Most lines installed. Cold patch at roadway crossings. |
| 04/01/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Working in shoulder, several crossings of Orchard, cold patch used as temp. patches. |
| 03/14/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Working in shoulder along Orchard. with barricades. |
| 03/04/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Working in shoulder along Orchard. with barricades. |
| 02/25/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Pre-con 11 am. Contractor to open cut all gas lines, just a couple of conctrete drive aprons and they will need to be replaced in full as well as the short section of sidewalk. |
| 02/22/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Contractor called - set up pre-con for 2/25 at 11 am. |