Permit: T19CM06028

Parcel: 11504475B


Addresses:

1055 N PARK AV


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T19CM06028

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
08/17/2021 EXCAVATION/LAYOUT REBAR & ZON Approved Approved
07/08/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Footing at AF-A16.
06/24/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Five small footings on column AB- Gridlines B2, B3.2, B3.6, B4, B5.
06/02/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Column footings at Garage level #2: GL: D.2/BB B.1/BB; B.2/BB.9; B.1/BC; B.1/BD. Ok to place concrete in progress areas.
05/29/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Not ready.
05/28/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Exterior wall grid line A16-AM thru AG.
05/27/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Not ready.
05/26/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Building B. Footings at gridline B1- BF& BE. Building A. Column AM gridline A5 thru A16.
05/22/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Footings at grid line B7- columns BA, BA.8, BB.1, BB.8.

Gridline B8- columns BB.8, BD.2, BE.2.

Exterior walls, Northeast corner arch down the east side to the pilaster.
05/21/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Building B. Footings at column BA-rows B2, B3.2, B4, B-5,
Column BD-rows B3, B4, B6, column BE-rows B3, B4, B6, column BF-row B3, B4, B6, BB-B6, BB.9-B6
05/20/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Building B, double mat for stairwell and two columns.
05/19/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Exterior wall from AA-A3 to North west corner, to East side arch.
05/18/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Columns at A10-AF.5, A4-AD, A4-AE, A1-AC.3, AA-A7. Ramp wall AA-A3 thru A10 and AF-A13 thru A18.
05/15/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Columns at AF-A14, AD-A-12, A-14-AH.2, A14-AJ.2, AB-A4.9, A3-AC, A1-AD6, AG-A4, AM-A15.4, AM-A13, AM-A11,AE-A6, AD-A6, AF5-A1,
AM-A9, AM-A5, AL-A5, AL-A2.3, AJ-A4, AG-A5.
05/14/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Columns on Gridlines A12- AG and AJ.3. Ramp wall at AF, A3 thru A12.
05/13/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval RVI Partial. Footings at gridlines AD.6-A2, AC.3-A2, AC-A3, AD-A4, A10-AF4. Exterior footing from A6 to AA, from AA to AE.

Columns at gridlines A2-AG, A2-AK, AJ-A5, AL-A9, AC-A7.
05/12/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval RVI Partial. Footing from A14 to A16, footing from AM to AH, from AH north to A15, from AH to AF. Columns at AH-A15, AJ.4-A16, and southeast corner
05/11/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Footings on columns AK, AL, AJ, AF.5, lower level column AC LINE A10 and A12, column AC.9 line A8 and A12. Exterior footing AE to AM, around the curve from AE to A14.
05/05/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval RVI Partial. Footings and columns, row A14 to column AA to AF; column AA to row A14 to A6; column AF to A14 to A7;
Columns at AC &A7, AC & A10, AC& A12, AD& A8.
05/04/2020 EXCAVATION/LAYOUT REBAR & ZON Cancelled Not Ready, cancelled.
05/01/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval RVI Partial. Tower crane foundation and two columns, located at column AD.9- rows A5 & A4.
04/29/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval ELEVATOR FOUNDATION ONLY