10/16/2020 PLUMBING - INTERMEDIATE Approved Approved
08/20/2020 PLUMBING - INTERMEDIATE Partial Approval Partial. Main water pump plumbed and operational.
08/14/2020 PLUMBING - INTERMEDIATE Partial Approval Partial. Elevator sump pumps in place and connected to discharge lines; power lines installed.
07/20/2020 PLUMBING - INTERMEDIATE Partial Approval Partial. Level #5; Room Units #501-536 and corridor ceilings.
07/17/2020 PLUMBING - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled
05/07/2020 PLUMBING - INTERMEDIATE Partial Approval Partial. Level #3; Waste and vent lines (2”-4”) in unit rooms in East and North wings.
04/27/2020 PLUMBING - INTERMEDIATE Partial Approval RVI Partial (VRI); Level #4; Waste and vent lines (2”-4”) and domestic hot/cold water lines in rooms #430-439. Level #5; Rooms 530-538.
04/23/2020 PLUMBING - INTERMEDIATE Not ready for Inspection Contractor cancelled. Will reschedule for 27 April.
04/22/2020 PLUMBING - INTERMEDIATE Partial Approval RVI Level #3; Waste and vent lines (2”-4”) and domestic water lines in rooms #512-529. Domestic water lines tested at 100 psi.
04/21/2020 PLUMBING - INTERMEDIATE Not ready for Inspection Contractor cancelled.
04/16/2020 PLUMBING - INTERMEDIATE Partial Approval RVI Waste and vent lines (2”-4) and domestic PEX water lines on Level #5; Rooms #501-511.
04/08/2020 PLUMBING - INTERMEDIATE Partial Approval RVI Level #4 North waste and vent lines at 2”-4”; Domestic water lines (PEX); Tested at 100psi. Level #4 East, Rooms: 415-433; in wall plumbing.
03/24/2020 PLUMBING - INTERMEDIATE Partial Approval Level #4 North; Waste and vent lines (2" - 4"). Level #3 East; domestic water lines tested at 110 psi.
03/23/2020 PLUMBING - INTERMEDIATE Not ready for Inspection Superintendent reported 2 workers sent home I’ll. My supervisor stated that I was not to be on site. Will attempt to set up for video inspection.
03/17/2020 PLUMBING - INTERMEDIATE Partial Approval Level #3; waste and vent lines at 2”-4” in rooms East side from stairs to end of corridor.
03/13/2020 PLUMBING - INTERMEDIATE Partial Approval Level #3; units from mid area to East Elevator, waste and vent lines at 2"-4".
03/11/2020 PLUMBING - INTERMEDIATE Partial Approval Supply lines for 2nd floor.
03/06/2020 PLUMBING - INTERMEDIATE Partial Approval Waste and vent lines (2"-4") at Level #3; North wing under hydro testing.
02/28/2020 PLUMBING - INTERMEDIATE Partial Approval Level #2; waste and vent lines (2”-4”) at Lobby area East to East side of building..
02/27/2020 PLUMBING - INTERMEDIATE Partial Approval Level #2, South Lobby area: waste and vent lines at 2” - 4”; under hydro testing.
02/19/2020 PLUMBING - INTERMEDIATE Partial Approval Level #2; Corridor #2106. GL: 12/D-M; waste and vent lines (2 1/2" - 4")
02/13/2020 PLUMBING - INTERMEDIATE Partial Approval Level #1 at Conference area restrooms: copper lines at 3/4"-2 1/2" under air test at 100 psi.
02/04/2020 PLUMBING - INTERMEDIATE Partial Approval Waste and vent lines (2"-4"); roof drains at 3" in North West section of building