Inspection Status: Approved
Inspection History: ELECTRIC - ABOVE CEILING
| Date |
Description |
Inspector |
Results |
Comments |
| 10/16/2020 |
ELECTRIC - ABOVE CEILING |
|
Approved |
Approved |
| 07/27/2020 |
ELECTRIC - ABOVE CEILING |
|
Partial Approval |
Partial. Level #6: Room units #601-636. |
| 06/22/2020 |
ELECTRIC - ABOVE CEILING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 06/03/2020 |
ELECTRIC - ABOVE CEILING |
|
Partial Approval |
Level #4; Unit Rooms #400-436. |
| 05/08/2020 |
ELECTRIC - ABOVE CEILING |
|
Partial Approval |
Partial. Level #2; Public Restrooms and Utility Room. Ok to cover ceilings in progress areas. |
| 05/07/2020 |
ELECTRIC - ABOVE CEILING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. Will reschedule for 8 May. |
| 04/27/2020 |
ELECTRIC - ABOVE CEILING |
|
Partial Approval |
RVI Partial (VRI); Level #2; canned lighting system in place. Ok to cover progress areas. |
| 04/21/2020 |
ELECTRIC - ABOVE CEILING |
|
Partial Approval |
Level #1, restrooms #050; 051; 053; 054; Corridor #16 and 16B. |
| 04/08/2020 |
ELECTRIC - ABOVE CEILING |
|
Not ready for Inspection |
(VRI). Contractor cancelled. RFI changes to be completed 4/8. |
| 04/08/2020 |
ELECTRIC - ABOVE CEILING |
|
Partial Approval |
RVI Level #2 East Over hang; can lightning system in place. |
| 04/07/2020 |
ELECTRIC - ABOVE CEILING |
|
Not ready for Inspection |
(VRI). Contractor cancelled. RFI changes to be completed 4/8 |
| 03/11/2020 |
ELECTRIC - ABOVE CEILING |
|
Partial Approval |
1st floor back of house hard lid areas. |