Inspection Status: Approved
Inspection History: BUILDING ABOVE CEILING
| Date |
Description |
Inspector |
Results |
Comments |
| 10/16/2020 |
BUILDING ABOVE CEILING |
|
Approved |
Approved |
| 09/25/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial. Level #1; Main Lobby area; bar area; coffee bar area. Duct work change in Lobby area as noted on plans. Ok to cover progress areas. |
| 09/10/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial. Level #1: Electric, Plumbing, Mechanical above ceilings in Meeting Room #4; South dining area; Main dining area; Coffee Bar, Retain space. Ok to cover progress areas. |
| 08/27/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial. Meeting rooms; lobby area; lobby corridors. Ok to cover ceilings. Ensure that penetrations are properly fire caulked. |
| 08/26/2020 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. Will reschedule for 27 August. |
| 08/12/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial. Level #1; Meeting rooms, ok to cover ceilings. Level #6; Room Units #601-639 and corridors. Ok to cover progress areas. |
| 07/31/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial. Elevator lobby areas on Levels #2-6. Ok to cover areas when fire system is in place. |
| 07/27/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial. Level #6; Room units at East and North corridors. |
| 06/22/2020 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 05/05/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial. Pool restrooms at Level #2; public restrooms #243; 244. Ok to frame and cover ceilings. |
| 04/27/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
RVI Partial (VRI); Level #2; Balcony, exterior soffit. |
| 04/21/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Level #1; Restrooms #050; 051; 053; 054; Corridor #16 and #16B. |
| 03/11/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
1st floor back of house hard lid areas. |