Permit: T19CM04184

Parcel: 11720029A


Addresses:

280 S CHURCH AV


Inspection Status: Approved

Inspection History: FRAMING

Permit Number - T19CM04184

Inspection Description - FRAMING

Inspection Status - Approved

Date Description Inspector Results Comments
10/16/2020 FRAMING Approved Approved
10/14/2020 FRAMING Approved Approved. Interior framing complete
08/27/2020 FRAMING Partial Approval Partial. Exterior lobby walls. Ok to insulate and cover walls
08/26/2020 FRAMING Not ready for Inspection Not ready. Contractor cancelled.
07/20/2020 FRAMING Partial Approval Partial. Level #1; exterior RCP Soffit (under pool area); West exterior RCP soffit. Ok to cover walls and ceilings. (Insulate and sheet rock).
06/26/2020 FRAMING Partial Approval Partial. Level #6; Unit Rooms East and North. Ok to insulate and cover walls.
06/22/2020 FRAMING Not ready for Inspection Not ready. Contractor cancelled.
06/17/2020 FRAMING Not ready for Inspection Not ready. Contractor cancelled.
06/03/2020 FRAMING Partial Approval Level #3; Corridors East and North. Level #4; Unit rooms #400 - 436. RC Channel. Ok to cover progress areas.
05/06/2020 FRAMING Partial Approval Partial. Level #3; Parapet walls at 24”; ok to cover and waterproof progress areas.
05/05/2020 FRAMING Not ready for Inspection Not ready. Contractor cancelled.
05/01/2020 FRAMING Partial Approval RVI Partial. (VRI). Level #3; parapet walls (East) at 10.5”-12”. Ok to cover progress areas.
04/29/2020 FRAMING Partial Approval RVI Partial. (VRI). Level: Roof; parapet walls at,48”-72”; kickers and clips in place.
04/28/2020 FRAMING Partial Approval Partial. Level #2; Unit Rooms #202-230; ceiling framing. Ok to cover progress areas.
04/27/2020 FRAMING Partial Approval Partial (VRI). Level #2; Balcony, Exterior soffit.
04/23/2020 FRAMING Not ready for Inspection Contractor cancelled.
04/22/2020 FRAMING Not ready for Inspection RVI Contractor cancelled
04/21/2020 FRAMING Not ready for Inspection
04/16/2020 FRAMING Partial Approval RVI Level #4, Light gauge and heavy gauge framing in rooms #410-439. Level #5; Rooms #501-540. Level #6; heavy gauge framing in rooms in East and West wings.
01/29/2020 FRAMING Partial Approval Level #1; Lobby area, kitchen area; support area, mechanical and electric areas. Ok to one side sheetrock in progress areas.
12/16/2019 FRAMING Partial Approval Courtesy inspection of new framing system.