Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit: T19CM04184

Parcel: 11720029A


Addresses:

280 S CHURCH AV

Inspection Status: Approved

Inspection History: REINFORCED MASONRY PRE-GROUT

Date Description Inspector Results Comments
10/16/2020 REINFORCED MASONRY PRE-GROUT Approved Approved
05/05/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at Southwest corner of site (Trash enclosure/generator room), at 56”. Ok to grout progress areas.
04/29/2020 REINFORCED MASONRY PRE-GROUT Not ready for Inspection
03/13/2020 REINFORCED MASONRY PRE-GROUT Partial Approval South site walls/pop-outs at 30"-54". Ok to place grout in progress areas.
01/24/2020 REINFORCED MASONRY PRE-GROUT Not ready for Inspection No inspection required, performed on 23 January.
01/23/2020 REINFORCED MASONRY PRE-GROUT Partial Approval CMU wall at 16’ top out on GL: 14.5/D-J.5. Ok to place grout in progress areas.
01/14/2020 REINFORCED MASONRY PRE-GROUT Partial Approval CMU Walls at GL: 13.85/J.5-A; A/12-13.75; all at 4’-8’. Ok to place grout in progress areas.
01/10/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Level #1; CMU wall topped out at 16’ 8” at GL: 14/J.5-L. Ok to place grout in progress areas.
01/08/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Level #1 CMU walls at GL: L/14; L-K.75; K.75/13.5-14; 13.75/H-K.5; A/12-13.75; 14/A-H: at 0’-4’; 13.75/K.5-H at 8’-12’. Ok to place concrete in progress areas.
01/02/2020 REINFORCED MASONRY PRE-GROUT Not ready for Inspection Will reschedule for 3 January early am.
12/30/2019 REINFORCED MASONRY PRE-GROUT Partial Approval Stairwell #1; Northwest and North CMU walls at 8’-12’, CMU walls at 0’-4’; at GL: K.5/14.5-13.8; 14.5/K.8-K; K/14.5-12. Ok to grout progress areas.
12/27/2019 REINFORCED MASONRY PRE-GROUT Cancelled Canceled by contractor due to rain.
12/26/2019 REINFORCED MASONRY PRE-GROUT Cancelled
12/23/2019 REINFORCED MASONRY PRE-GROUT Partial Approval Stairwell #1; Northwest wall at 4’-8’. Ok to grout progress areas.
12/20/2019 REINFORCED MASONRY PRE-GROUT Not ready for Inspection Mason foreman cancelled, will reschedule for 23 December.
12/18/2019 REINFORCED MASONRY PRE-GROUT Partial Approval North CMU wall at GL: M/10-12; top out. Ok to set anchor bolts.
12/16/2019 REINFORCED MASONRY PRE-GROUT Partial Approval CMU wall at GL: M/10-12; 4’-8’. Ok to place grout.