Permit: T19CM04184

Parcel: 11720029A


Addresses:

280 S CHURCH AV

Inspection Status: Approved

Inspection History: BUILDING PRE-SLAB

Date Description Inspector Results Comments
10/16/2020 BUILDING PRE-SLAB Approved Approved
04/08/2020 BUILDING PRE-SLAB Partial Approval RVI Level #7 (Roof) East slab; #4 Wire mesh and rebar enforcement. Ok to place concrete in progress area.
03/24/2020 BUILDING PRE-SLAB Partial Approval Level #7 North; deck slab: rebar and wire mesh reinforced. Ok to place concrete in progress area.
03/12/2020 BUILDING PRE-SLAB Partial Approval Level #6 East; wire mesh and rebar reinforcement in place. Ok to place concrete in progress areas.
03/03/2020 BUILDING PRE-SLAB Partial Approval Level #6; North and Southwest slab area. Metal decking with #4 wire mesh over laid and #4 & #5 rebar. Ok to place concrete in progress areas.
02/25/2020 BUILDING PRE-SLAB Partial Approval Metal decking system; #4 mesh; rebar; Level #5 East slab. Ok to place concrete in progress area.
02/24/2020 BUILDING PRE-SLAB Not ready for Inspection Contractor cancelled; will reschedule for 25 February.
02/04/2020 BUILDING PRE-SLAB Partial Approval Metal/rebar deck system at Level #4 East. Ok to place concrete. Blankets and weather protection must be place on finished concrete due to inclement weather.
01/29/2020 BUILDING PRE-SLAB Partial Approval Level #4; West deck; #4 wire mesh and rebar on a metal deck. Ok to place concrete in progress area.
01/10/2020 BUILDING PRE-SLAB Partial Approval Level #3; North: rebar and wire mesh in place. Ok to place concrete in progress area.
01/08/2020 BUILDING PRE-SLAB Partial Approval Level #3; GL: B.5/5-6; 6/A-B.5; 1-5/A-H; 5.75/A. Ok to place concrete in progress areas.
12/03/2019 BUILDING PRE-SLAB Partial Approval Post Tension Cable System at Level #3; GL: A-H/5-13. Ok to place concrete.