Permit: T19CM04184

Parcel: 11720029A


Addresses:

280 S CHURCH AV


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T19CM04184

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
10/16/2020 EXCAVATION/LAYOUT REBAR & ZON Approved Approved
03/06/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Generator pads at Southwest portion of site (2). Level #6; Elevator shear walls; Ok o set forms and place concrete.
02/28/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval South and Southwest site wall footings: approximately 70 feet. Ensure footings are cleaned of debris. Ok to place concrete in progress areas.
02/27/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #5 to Level #6 on Stairwell #1: shear walls, North and South. Ok to place concrete in progress areas.
02/19/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #5; Stairwell #1; shear walls. Ok to place concrete in progress areas.
02/12/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #5; Northwest Stairwell shear walls. Ok to place concrete in progress areas.
02/06/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #2; Stairwell #2 shear walls. Ok to place concrete in progress areas.
02/03/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #4; Stairwell #1 North, shear walls. Ok to place concrete in progress areas.
01/16/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Sw 3,4,5,6 elevator shaft. - e - g. 10 - 11.5. Level 4 - 5 ok to pour
01/14/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Stairwell #1; shear walls on Levels 3-4; GL: M/12-14; L/12-14. Ok to place concrete in progress areas.
01/07/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #2; Pool/Deck area at GL: 11.5/110-111; 110/11.5-7; 7/110-111; 111.5/11.5-7. Ok to place concrete in progress areas.
12/12/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #3; elevator shear walls #3;4;5. Ok to set forms and place concrete in progress areas.
11/27/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Shear walls at Level #2; GL: 2.5/A B; shear wall at Level #3; GL: 2.5/A-B. Ok to place concrete in progress areas .
11/21/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Rained out.
11/19/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Level #2-3; columns at GL: A/9; A/13. Ok to place concrete in progress areas.