Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 10/16/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
Approved |
| 03/06/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Generator pads at Southwest portion of site (2). Level #6; Elevator shear walls; Ok o set forms and place concrete. |
| 02/28/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
South and Southwest site wall footings: approximately 70 feet. Ensure footings are cleaned of debris. Ok to place concrete in progress areas. |
| 02/27/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Level #5 to Level #6 on Stairwell #1: shear walls, North and South. Ok to place concrete in progress areas. |
| 02/19/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Level #5; Stairwell #1; shear walls. Ok to place concrete in progress areas. |
| 02/12/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Level #5; Northwest Stairwell shear walls. Ok to place concrete in progress areas. |
| 02/06/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Level #2; Stairwell #2 shear walls. Ok to place concrete in progress areas. |
| 02/03/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Level #4; Stairwell #1 North, shear walls. Ok to place concrete in progress areas. |
| 01/16/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Sw 3,4,5,6 elevator shaft. - e - g. 10 - 11.5. Level 4 - 5 ok to pour |
| 01/14/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Stairwell #1; shear walls on Levels 3-4; GL: M/12-14; L/12-14. Ok to place concrete in progress areas. |
| 01/07/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Level #2; Pool/Deck area at GL: 11.5/110-111; 110/11.5-7; 7/110-111; 111.5/11.5-7. Ok to place concrete in progress areas. |
| 12/12/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Level #3; elevator shear walls #3;4;5. Ok to set forms and place concrete in progress areas. |
| 11/27/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Shear walls at Level #2; GL: 2.5/A B; shear wall at Level #3; GL: 2.5/A-B. Ok to place concrete in progress areas . |
| 11/21/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
Rained out. |
| 11/19/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Level #2-3; columns at GL: A/9; A/13. Ok to place concrete in progress areas. |