Permit: T19CM04078

Parcel: 141390230

Inspection Status: Approved

Inspection History: FRAMING

Date Description Inspector Results Comments
06/01/2020 FRAMING Approved
05/18/2020 FRAMING Partial Approval Partial, Framing for plumbing walls on demising fire assembly ok to Insulate and Sheetrock these locations all units.
04/10/2020 FRAMING Partial Approval Decking and crickets
03/16/2020 FRAMING Partial Approval Shear walls third floor Only
02/21/2020 FRAMING Partial Approval Inspection of 3rd floor Deck Approved.
02/12/2020 FRAMING Partial Approval Interior Clips and straps for 1st floor to 2nd floor connections inspected & Approved.
01/13/2020 FRAMING Partial Approval Floor decking for 2nd floor ok.
01/10/2020 FRAMING Partial Approval first floor